46 – With respect to idle resources:
* Are/have contractor personnel and equipment sitting/been idle for an extended period of time? (Yes = bad: Cost/audit issue)
* Did long delay occur between mobilization/assembling resources and the actual start of the project? (Yes = bad: Cost/audit issue)
* A sufficient cushion exists to protect the project from unexpected setbacks? (No = bad)
47 – Are people working unusually fast? (Yes = blue possibly a safety issue)
48 – Can SM/PM give an objective estimated time to complete to achieve higher output? (No = bad)
49 – Does SM/PM use a multi-disciplinary team to resolve actual/potential issues? (Yes = good) Does it include people from:
* Operations
* Planning
* Finance
* Labor relations
*Safety