SAMPLE PERFORMANCE/EARNED VALUE REPORT

Directorate Support Group:        Research & Technology
Directorate Support SubGroup: Research & Technology Program (RTP)

Monthly (x $1,000) Prior Year Oct-02 Nov-02 Dec-02 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03
BCWS – Plan ($) $100 $200 $200 $200 $200 $200 $200 $200 $200 $200 $200 $200 $200
BCWP – Performance ($) $100 $150 $150 $150
ACWP – Actual ($) $100 $250 $250 $250
ETC – To Go ($) $100 $250 $250 $250 $200 $200 $200 $200 $200 $250 $200 $200 $200
CV – Cost Variance ($) $0 ($100) ($100) ($100)
SV – Schedule Variance ($) $0 ($50) ($50) ($50)
Cumulative (x $1,000) Prior Year Oct-02 Nov-02 Dec-02 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03
BCWS – Plan ($) $100 $300 $500 $700 $900 $1,100 $1,300 $1,500 $1,700 $1,900 $2,100 $2,300 $2,500
BCWP – Performance ($) $100 $250 $400 $550
ACWP – Actual ($) $100 $350 $600 $850
ETC – To Go ($) $100 $350 $600 $850 $1,050 $1,250 $1,450 $1,650 $1,850 $2,100 $2,300 $2,500 $2,700
CV – Cost Variance ($) $0 ($100) ($200) ($300)
SV – Schedule Variance ($) $0 ($50) ($100) ($150)

VARIANCES (Favorable is positive, Unfavorable is negative)

  • Cost Variance CV   = BCWP – ACWP         CV % = CV / BCWP
  • Schedule Variance SV    = BCWP – BCWS         SV %  = SV / BCWS
  • Variance at Completion VAC = BAC – EAC

 PERFORMANCE INDICES

  • Cost Efficiency CPI      =          BCWP / ACWP
  • Schedule Efficiency SPI      =          BCWP / BCWS

OVERALL STATUS

  • Percent Complete =    BCWP CUM          BAC
  • Percent Spent =    ACWP CUM     BAC

TO COMPLETE PERFORMANCE INDEX (TCPI)

TCPI                                                    =    WORK REMAINING           =          BAC – BCWP CUM

(EAC)                                                        COST REMAINING                              EAC – ACWP CUM

ESTIMATE AT COMPLETION         (EAC = ACWP + Estimate for Remaining Work)

EAC     =       BAC_ _    ∙ EAC Composite= ACWP CUM +            BAC=BCWP CUM  _                CPI             CPI CUM                      (CPI CUM) ∙ (SPI CUM)