Implies:
- Scheduled work has not been done
- Labor disputes/work stoppage
- Insufficient staffing/manpower shortage/other resources
- Associated labor costs have not been incurred
- An ineffective & efficient process
- Low quality (productive) work with below average costs
- Work being done at less than 100% efficiency
- Supporting organizations behind schedule
- Late vendor delivery
- Delayed customer feedback/direction
- Rework required
- Work more complex than anticipated
- Unclear requirements
- Scope creep could tend to obscure the bad news, giving a false sense of security
-
Note:
Anticipate a cost overrun. Schedule does not reflect reality. This is one of the worst possible cases.
Note: Please associate this slide with the Earned Value Chart